Electronics design begins immediately upon receipt of funds.. purchase _all_ electronics materials immediately. Expected at least 1 month for boards to be delivered, minimum 3 months to assemble, and need 2 months to complete all programming. This is the key part of the project, and will require considerable time, a 7 month schedule for the electronics. estimated (but likely more because its software) 825 hours. The steel can be purchased locally, and due to the repetitive nature will be a fairly straightforward process. Two alignment jigs will be made for the penta and hexa vertex to insure accurate alignments. All machining must be completed in order to facilitate final testing and programming. estimated hours for structure fabrication 570. All construction and fabrication will be completed before playa, so LNT is simply disassemble and pack it back home. |